Project Closure & Handover Guideline
Department
Table of Contents
| Section | |
|---|---|
| 1 | Purpose |
| 2 | Scope |
| 3 | Definitions |
| 4 | Operating Model (Sprint + Asana + Visibility) |
| 5 | Roles & Responsibilities |
| 6 | Step-by-Step Process |
| 7 | Project Closure Checklist (PM Use) |
Purpose
This guideline defines how Kiluth closes a project after go-live: confirm final acceptance, deliver a handover package, decide whether a short stabilization window is needed, and record closure in Asana.
| Outcome |
|---|
| The client acceptance proof and handover links are easy to find, and “closed vs ongoing” status is explicit in Asana. |
Scope
This guideline covers the workflow from “go-live verified” through:
| Included | |
|---|---|
| 1 | Final acceptance confirmation and sign-off proof linking |
| 2 | Handover package preparation and delivery |
| 3 | Transition to hypercare/support (if applicable) or closure |
| 4 | Closure record in Asana (what’s done, what’s outstanding, next owner) |
This guideline does not replace detailed incident/support operations. If the project transitions into ongoing support, reference Technology/Support playbooks as needed.
Definitions
| Term | Definition |
|---|---|
| Handover package | The minimum set of artifacts the client needs to operate/maintain the system (links, credentials handling notes, runbooks, etc.) |
| Final acceptance | The client’s confirmation that the delivered scope is acceptable (per agreed acceptance criteria / contract) |
| Closure record | A short summary in Asana of what shipped, what was accepted, what remains (if anything), and where the proof links live |
| Hypercare | A short stabilization period after go-live where the team prioritizes rapid response |
Operating Model (Sprint + Asana + Visibility)
| Operating Model | |
|---|---|
| 1 | Asana is the system of record for work tracking, approvals, and handoffs. |
| 2 | Use checkpoints and decision points: don’t move forward until the previous step is “done”, and branches are explicit. |
| 3 | Handoff order: upstream defines handoff artifacts/exit criteria; downstream defines execution after handoff. |
Roles & Responsibilities
| Role | Responsibility |
|---|---|
| Project Manager (PM) | Drives closure workflow, ensures artifacts/checklist completion, updates closure record in Asana |
| Account Executive (AE) | Owns client coordination for acceptance confirmation/sign-off proof and keeps the “latest meeting minutes” sign-off proof link up to date |
| Technology / Creative (implementation owner) | Provides technical handover artifacts (runbooks, access notes, deployment notes as applicable) |
| Finance | Confirms payment status when needed for closure decisions |
| Legal | Validates closure-related documents when contractual terms require it |
Step-by-Step Process
| Step | |
|---|---|
| 1 | Confirm go-live verified: link the go-live task and its verification result from the project card |
| 2 | Confirm final acceptance: AE collects sign-off proof and links it (Sign-off proof: [Link]) |
| 3 | Prepare handover package: PM collects links/artifacts below and posts them in the closure task |
| 4 | Handover walkthrough (only when needed): schedule a short session, then link meeting minutes + sign-off proof |
| 5 | Decide stabilization window vs close: record the decision + dates in Asana (no “silent” ongoing work) |
| 6 | Write the closure record in Asana and move any remaining tasks to the correct owner/board |
Minimum handover package (default)
| Provide (as links in Asana) | |
|---|---|
| 1 | Handover package folder/file link(s) |
| 2 | Operating notes / runbook (how to use, how to recover common issues) |
| 3 | Deployment/go-live notes (if applicable) |
| 4 | Where logs/monitoring live (if applicable) |
| 5 | Access/credentials handling notes (never paste secrets into Asana) |
Decision point: hypercare vs close
| Outcome | Action |
|---|---|
| Stabilization window (hypercare) | Record window + owners + escalation path. Track issues in Asana and record “exit hypercare” explicitly. |
| Close | Proceed to closure record and mark closure completion. |
Asana Card Template: Project closure & handover
| Asana Card Template | |
|---|---|
| Title | Project closure & handover – [Client Name] – [Project Title] |
| Assignee | Project Manager |
| Description | Please close this project using this checklist. References • Project card: [Link] • Go-live task: [Link] • Signed brief / SOW: [Link] Acceptance • Sign-off proof: [Link] (final acceptance) • Optional quote (1 line): [Quote] Handover package • Handover package link(s): [Links] • Runbook / operating notes: [Link] • Access/credentials handling notes (no secrets in Asana): [Notes/link] Decision • Hypercare: Yes/No • If yes: window + owner: [Dates/name] Closure record (fill when done) • What shipped: [Short] • What’s accepted: [Short] • Outstanding items (if any) + next owner: [Short] • Where proofs live: [Short links] |
Asana Card Template: Collect final acceptance sign-off
| Asana Card Template | |
|---|---|
| Title | Collect final acceptance sign-off – [Client Name] – [Project Title] |
| Assignee | Account Executive (AE) |
| Description | Please collect final acceptance confirmation from the client (per acceptance criteria / contract). References • Project card: [Link] • Go-live verification summary: [Link] • Acceptance criteria reference: [Link/section] Final acceptance • Sign-off proof: [Link] (stored/linked by AE; AE owns upkeep) • Optional quote (1 line): [Quote] Note: if the acceptance decision affects contract-related decisions, use a signed document. |
Project Closure Checklist (PM Use)
Preconditions
| Checklist | |
|---|---|
| 1 | ☐ Go-live is verified (linkable) |
| 2 | ☐ Project scope reference is clear (signed brief / SOW linked) |
Final acceptance
| Checklist | |
|---|---|
| 1 | ☐ Sign-off proof: [Link] (final acceptance; AE owns upkeep) |
| 2 | ☐ Latest meeting minutes sign-off proof link is up to date (AE owns upkeep) |
Handover package
| Checklist | |
|---|---|
| 1 | ☐ Handover package delivered (links provided) |
| 2 | ☐ Runbook/operating notes delivered (when applicable) |
| 3 | ☐ Access/credentials handling plan is documented (no secrets in Asana) |
Hypercare / support transition (if applicable)
| Checklist | |
|---|---|
| 1 | ☐ Decision recorded: hypercare vs close |
| 2 | ☐ If hypercare: window + owners + escalation path recorded |
| 3 | ☐ Exit hypercare recorded (if used) |
Closure record
| Checklist | |
|---|---|
| 1 | ☐ Closure record completed in Asana (what shipped / accepted / outstanding + next owner) |
| 2 | ☐ Project card status reflects closure (or transitions to support board if ongoing) |